Brace for Heavier Traffic in Metro Manila due on going road construction and repair

By Nelson Flores, Ll.B., MSCK

(File photo) Workers doing reblocking along the  South bound lane of Cubao Tunnel. Photo by Michael Varcas.

THE Metropolitan Manila Development Authority warned the public Friday to expect heavy traffic in the second half of the year as simultaneous road construction and repair works begin in different locations in Metro Manila.

Among these projects are North Luzon Expressway Drainage Enhancement Project along A. Bonifacio Road beginning July 1; construction of an elevated guideway for the Metro Rail Transit 7 (MRT-7) along North Avenue beginning July 2; emergency leak repair on a large mainline along EDSA-Shaw Boulevard area starting July 7 and replacement of Buendia Bridge also beginning next month.

We acknowledge that these projects will cause heavy traffic all-year-round but we cannot compromise the safety of the motorists. If there is an urgent need to do these road projects simultaneously, then we will give the necessary clearances,” MMDA General Manager Jose Arturo “Jojo” Garcia told newsmen during a press press at the agency’s headquarters in Makati City.

MMDA Acting GM Jose Arturo Garcia. Image © Rappler

Garcia also said that in anticipation of the massive inconvenience that these projects would bring, the Metro Manila Council (MMC) has approved a resolution, regulating the operation of provincial buses along Edsa.

Starting July 15, all provincial buses will be strictly prohibited from operating along EDSA from Pasay City until Cubao, Quezon City, both northbound and southbound, from 5 am until 10 am and from 4 pm until 9 pm, from Monday to Friday.

All provincial buses from the north can traverse EDSA only until Cubao while provincial buses from the south can traverse only until Pasay during morning and afternoon till late evening rush hour during weekends,” said Garcia.

Affected provincial bus terminals are exempted from the Unified Vehicular Volume Reduction Program (UVVRP) or number coding scheme. They are also allowed to use the MMDA-operated Southwest Interim Provincial Terminal (SWIPT) located in Pasay City.

We expect to reduce by 2,000 provincial buses traveling along EDSA once the regulation is implemented,” said Garcia.

Violators of the ban will be meted with PhP2, 000 fine.

(File Photo) An ordinary day on EDSA © balita.com

List of road construction and repair works.

1. NLEX Drainage enhancement project along A. Bonifacio Road beginning July 1.

The NLEX Drainage Enhancement Project will be undertaken at a portion of Balintawak Cloverleaf along A. Bonifacio Avenue Road from 11 pm to 4 am for 70 to 80 days. To give way for this project, the ramp of Balintawak Cloverleaf EDSA-South bound will be closed to vehicular traffic.

Motorists are advised to take the following alternate routes:

Route 1: Vehicles coming from NLEX should take Smart Connect Interchange to Mindanao Avenue to destination. Exit to EDSA Monumento-bound and make a U-Turn to EDSA Southbound.

Route 2: Vehicles coming from Monumento to A. Bonifacio Avenue should turn right to Biglang Awa Street, left at Jasmine Street, straight to 11th Avenue, turn right at A. Bonifacio Avenue to destination.

2. Construction of an elevated guideway for the MRT 7 along North Avenue beginning July 2.

Private contractor EEI Corporation will expand their working area on North Avenue in Quezon City for the construction of an elevated guideway for the MRT-7 starting July 2.

The elevated guideway will be put up on North Avenue, from Mindanao to Veterans Hospital Gate area in the jurisdiction of Bagong Pag-asa and Project 6.

Construction will be done in two phases: from Veterans to Vertis North Gate and from Vertis North Gate of Mindanao Avenue.

3. Emergency leak repair on large main line along EDSA-Shaw Boulevard area starting July 7.

Water concessionaire Manila Water will conduct an emergency leak repair on its large mainline on EDSA-Shaw Boulevard southbound area.

Pre-construction works will begin July 7 while construction proper will be undertaken on a 24/7 schedule starting July 14 until the next 30 days.

Vehicles turning right from EDSA to Shaw Boulevard will be diverted to Starmall premises to allow southbound buses and private vehicles to use the service road exclusively.

4. Replacement of Buendia Bridge also in July.

The Department of Public Works and Highways (DPWH) is also set to build a stronger new Buendia Bridge along Buendia Avenue. The current Buendia Bridge has been found with cracks and needs immediate replacement due to poor condition.

The MMDA has yet to give clearance for the construction of the new bridge that will be done in two phases.

 

BD Admin: You think your friends gonna like this piece? If you do, kindly share it. Thanks.

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.